The Challenge
In a context where electric vehicle (EV) users demand charging power above 100 kW to reduce waiting times, the Miralbueno Service Station faced a significant challenge::
⚡Grid connection limited to 100 kW
🏢 Station consumption: 40 kW
🔌 Only 20 kW available per hose for EV charging
To install a 180 kW charging point, it was necessary to implement a solution that could::
The Solution
BeePlanet addressed these challenges with a modular solution that combines energy storage, intelligent management with BHive® and progressive charging capacity expansion.
📌PHASE 1: 2022 // The initial solution consisted of installing a storage system with a capacity of 100 kW and 126 kWh, accompanied by the BHive®energy manager, which centralized the management of photovoltaic (PV) generation, the 180 kW charger, and station consumption.
📌PHASE 2: 2023 // With the increase in charging demand, the storage system was expanded by adding another 100 kW and 230 kWhsystem, allowing for unrestricted 180 kW charging for users, greater optimization of available power, and a significant reduction in wait times.
📌PHASE 3: 2024 // For the installation of a second 180 kWcharger, a BCube was added® Compact 100 kW and 240 kWh, achieving efficient management of up to 360 kW at charging points.